Forest Road Drainage Installation Practices
in the Pacific Northwest Navigation text
Navigation bar (text links below) Home Table of Contents section 01 section 02 section 03 section 04 section 05 section 06 section 07 section 08 section 09 section 10 section 11 section 12 section 13 section 14 section 15 section 16 Additional Information
13 - Erosion Protection Stream Culverts, Cross Drains, Bridges

Pipe Culverts in Non-Fish Bearing Streams

Intakes may be placed slightly above the stream bottom to create the effect of a catch basin. If there is a risk of erosion at the intake, place armour so that it is flush with the intake when the installation is complete. Otherwise, if some of the flow can bypass the culvert intake, back eddying may prevent an unobstructed water flow through the culvert. Install proper ditch blocks. Always protect culvert outlets by rock. If there is a risk of channel down-cutting from outlet fall, place armour below outlet and some distance downstream.

Pipe Culverts in Fish-Bearing Streams

Pipe culverts in fish-bearing streams must be embedded in the stream channel to ensure fish passage. Armour protection must prevent erosion of fill and streambed material from around intakes and outlets. Pay particular attention to the depth and slope of the pipe to avoid the development of a plunge pool. Ensure that bedding material around the pipe receives proper compaction during the installation.

Figure 3: Armour Below Scour Depth
diagram: armour below scour depth

Armour

It should be angular and well graded, and 50% should be 10% bigger than the biggest rocks moved by peak flows. Place armour below scour depth and force it into the soil with the excavator bucket. Simply "sprinkling" rock around intake and outlet is very ineffective and expensive. Avoid using round river rock as armour if possible.

Cross Drains

(Ditch Culverts) Cross drains are an important component of drainage system maintenance and ditch management. They drain ditch water accumulations from seepages and surface runoff to the low side of the road prism. To prevent erosion, armour culvert outflows from outlet to natural stable forest floor. If cross drains are protruding from the fill, place rock or other energy dissipators below the outfall for low water levels and for peak flows. Cross drains are important for diverting sedimentladen ditch water onto vegetated slopes away from streams.

Bridges and Open-Bottom Structures

The base of these structures should be placed below the scour depth to reduce the risk of erosion. Armour as in pipe culverts above. If site conditions do not allow the placement of footings below the scour depth, armour must protect the substructure (log cribs, pre-cast footings or lock blocks) without encroaching on the stream, or pinching the flow. Armour must be placed well below the scour depth of the stream.

Erosion Protection of Fine-Textured Soils

End fills and bedding materials should always be coarse grained. If fine-textured soils must be used in approach fills, cover the fill with geotextiles before placing the erosion protection. The geotextile layer will prevent the erosion of even small soil particles from underneath the armour. Ensure proper fill slopes and material compaction.

Use geotextile on stringers and in cribs to retain fill Compact fill material Armour below scour depth Figure 3: Armour Below Scour Depth Leave streamside vegetation undisturbed

13 - Erosion Protection
 
Back Back Top of Page Top of Page
Home Home
Table of Contents Table of Contents  
Next Next
PLANNING ISSUES  
Introduction  1  section 01
Site Selection  2  section 02
Diversion Plans  6  section 06
Other Issues  7  section 07
  INSTALLATION PRACTICES
section 09    9  Compaction
section 10  10  Fisheries Issues
section 11  11  Diversion Dams
section 12  12  Ditch Management
section 13  13  Erosion Protection
section 14  14  Sediment Control
section 15  15  Culvert Position
©1999 - 2001 Flip Productions Limited
Used with permission by CulvertBC